Stadia

Corestruc’s pre-cast concrete systems have been used to build the bulk of the grand stands on a host of sports complex projects.

Our systems comprise columns, raker beams and seating benches that are rapidly assembled on site.

The 90 metre-long pavilion for the Sekgopa sport stadium was installed in as little as eight working days, with similar production rates achieved on the construction of the Lebaka sport complex.

Successes achieved on these two projects opened an entire new market for us.

One of our latest projects is a 2 500-seater pavilion for Collins Chabane Local Municipality.

Corestruc’s team arrived on site once A & P Civils & Trading had completed the earthworks and site terracing.

After casting the concrete bases and installing the connection bolts, the columns were fixed in position and aligned.

The main contractor was able to commence with the brick works at the front of the grand stand to accelerate the works while Corestruc started placing the raking columns.